|
Charlotte's Whitewater Center
Contractors, Designer Ride the
Rapids into the Unknown
By Bea Quirk
The world's first self-contained artificial river became
operational last month in Charlotte. To create the $32 million
U.S. National Whitewater Center, two Charlotte firms, Liquid
Design and RodgersDooley, utilized technology from around
the globe, as well as their own innovative thinking.
It's surprising, even for longtime residents, to realize
that just 10 minutes from downtown Charlotte's office buildings,
condo towers and hustling crowds, the Catawba River flows
through a forested landscape with only a few scattered homes.
But now something has been created in this rural pocket that
has attracted the attention of people from around the globe:
the world's first multiple-channel artificial river using
a closed-loop system, which went operational in July.
Visitors to the $32 million U.S. National Whitewater Center
- from Olympic-caliber kayakers to folks just wanting a casual
fun rafting experience - will be able to ride the rapids on
a curving up-and-down course starting at an upper pool and
rafting down a channel that drops 21 ft. to a lower finishing
pool.
With the water flowing at 800-900 cu. ft. per second, and
boulders carefully placed to recreate the rapids of a natural
rocky stream, the rafters should get their share of thrills
during the typical 1.5-hour experience.
When they're done, they can jump onto a conveyor belt system
to return to the top of the course and repeat the experience.
The 4,000-lin.-ft.-long artificial river, which is on 50 acres,
is also being used as a training facility for competitive
kayakers and as a site for competitive events.
There are other, similar manmade facilities - the most notable
one is in Sydney, Australia, which was used for the 2000 Olympics.
But in those, the water is supplied by an adjacent river.
Even though the Charlotte facility is also located on a river,
it doesn't draw water from it, making the system self-contained.
"We had to deal with several jurisdictions, and the
red tape was so hard to overcome, it could have taken us years
to get all the authorizations (to draw from the river),"
said Michael Williams, president of Liquid Design, the Charlotte
architectural/ construction management company that designed
and managed the project. "It made more sense to create
our own pond, and it was more cost-effective to keep using
the same water."
The 12 million -14 million gallons of water needed to fill
the artificial river comes from the Charlotte Mecklenburg
Utilities Department, which had an existing pumping station
near the new facility. To ensure efficiency, the center built
another station, as well as a 2,000-ft.-long line, so it is
directly connected to the CMUD system.
The actual sitework began in March 2005, but the design work
began about two years earlier. The general contractor, Charlotte-based
RodgersDooley, was involved from the start, as was consultant
Scott Shipley, an Olympic kayaker who also is a mechanical
engineer.
"He dealt with the water and made sure it does what
it's supposed to do," said Williams, who was the project's
lead designer. RodgersDooley is an alliance between Rodgers
Builders and RT Dooley, both of Charlotte. Liquid Design and
RodgersDooley are also creating the conference center/restaurant
and the climbing center, which are being completed this summer.
The nonprofit facility also includes indoor and outdoor climbing
areas, a ropes course, 11 mi. of trails and a 20,000-sq.-ft.
conference center/ restaurant. The center is located on Mecklenburg
County's 300-acre Historic Tuckaseegee Ford District Park
near the intersection of interstates 85 and 485. The trails
- for walking, hiking, jogging and mountain biking - were
in place before the center was established.
Monies have been raised from the private sector and will
also come from the proceeds of operating the center. There
has been no direct government funding, but Mecklenburg County
and several neighboring towns have guaranteed the loans.
"It (the artificial river) was unusual, and no one knew
how to build one, and no one knew what it would cost,"
said Scott Carr, Rodgers' senior project manager. "There
were so many unknowns, and we had to convince the building
inspectors it was safe."
That was especially true when all they had was a concept.
"We all did lots of research, and evaluating systems
became an art," Carr added. "We went through tons
of schematics. It became all about working together as a close-knit
team. This has been awesome and a lot of fun, one of the best
projects I've worked on. I'd love to start another one tomorrow."
Jeff Wise, the center's executive director, said it was important
to the team to build a facility that was known for aesthetics,
durability and functionality, as well as something that was
user-friendly for both novices and world-class athletes. "That
was a tall order," he added. "But the design and
construction team has given us everything we asked for."
Going into the unknown offered a variety of challenges. Pumping
and filtering the water was a major concern. The pump system
is made up of seven submergible pumps made by ITT Flygt of
Sweden.
The system, which Williams said is the largest ever assembled
for a whitewater park, cost $1.2 million and is capable of
pumping 536,000 gallons per minute. That's fast enough to
fill an Olympic-sized swimming pool in nine seconds.
A filtration system supplied by PEP Filters of Israel will
purify the water through ultraviolet treatment instead of
traditional chlorine. The price tag was another $1 million.
Because of the fast-track construction schedule, a plan was
devised to prevent possible rain delays. As soon as portions
of the channel were dug and a liner installed, the concrete
was poured to a 6- to 8-in. thickness.
"They chased each other around the course," Carr
said. Concrete pouring began last August and was completed
in June.
Instead of shotcrete, traditional cast-in-place concrete
was used. To improve the water's flow, the concrete needed
to be as smooth as possible. To finish the concrete, Rodgers
staffer Mark Cassel designed a jig that was attached to the
fork lift that smoothed the concrete out after it was poured.
It was dubbed 'The Castle' in his honor.
Altogether, RodgersDooley laid about 15,000 yds. of concrete.
The center was spared the recent dramatic increase in the
cost of concrete because the company locked in the price about
two years ago.
To minimize the potential for damage to the welded liner
under the concrete and decrease the amount of concrete cracking,
RodgersDooley used a fiber additive instead of wire mesh in
the concrete. Vents were added to help relieve pressure on
the concrete, especially in the lower pool.
Still, Carr conceded there will be water loss - up to 100,000
gallons a day - from leakage, splashing, filter backwash and
evaporation.
Jeff Gustin, vice president of Liquid Design, acted as senior
project manager for the artificial river and coordinated the
work of 24 subcontractors, who had as many as 200 workers
onsite at one time.
Those subs had to be convinced they could do the work because
"it wasn't the typical job they did every day,"
Carr said. "But we broke the work down and showed them
they could do it cost-effectively and quickly."
RodgersDooley took responsibility for erosion-control monitoring
of the site instead of handing it off to the site coordinator.
The center sits on the Catawba's dirtiest tributary, Long
Creek, where runoff is a major problem.
"This was just too important to us," Carr said.
To prevent further damage to the river from construction,
Rodgers personnel took classes on erosion control and used
double-silt fences and multibaffled erosion control ponds
on the site.
Despite its name, Liquid Design had no previous whitewater
park experience. (Liquid refers to the company's flexibility,
Williams said.)
But Williams added that he is now eager to use what he learned.
"Charlotte won't be the last of these super parks, and
now that we have figured out the technology, we can put one
in anyone's backyard," he said.
|